Quantcast
Channel: PrimaveraBlog, Tutorials, Project Management,P3,P3ec » Budget at Completion
Viewing all articles
Browse latest Browse all 3

Techniques for Computing Estimate to Complete

$
0
0
Estimate to Complete (ETC) in PM terminology mean the amount that is left to spend. Primavera calculates ETC for every activity where cost is allocated. It help us to forecast the Estimate at Completion (EAC) which is calculated as Estimate at Completion = Actual Cost + Estimate to Complete. Actual Cost is into put every [...]

Viewing all articles
Browse latest Browse all 3

Latest Images

Trending Articles



Latest Images